EXPERIENCE LIST FOR MAJOR PROJECTS OF 2017 FOR PROCESS EQUIPMENT DIVISION

 

SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
1 SAUDI ARAMCO CORROSION INHIBITOR INJECTION SKIDS – 4 Nos. TO BE COMPLETED
Z018-C531 – SHEDGUM STORES (for HARMALIYAH Project) August 2017
2 DENYS ARABIA COMPANY LTD. HOLDING TANKS – 4 Nos. ASME U stamp TO BE COMPLETED
Saudi Aramco – Replace Three Northern SHELL ID 1,500 mm x Length 6,500 mm x Thk 10mm = 2 Nos October-17
Area Pipeline Project – Jubail SHELL ID 1,100 mm x Length 6,000 mm x Thk 10mm = 2 Nos.
Materil: SA 516 Gr.70+HIC
3 Tamimi Global Co. Ltd. (TAFGA) DIESEL TANKS – 6 Nos. UL – 142 TO BE COMPLETED
SHELL ID 2,600 mm x TL-TL Length 6,500 mm x Thk 8mm = July-17
SHELL ID 1,100 mm x Length 1,520 mm x Thk 8mm = 3 Nos.
Materil: SA 36
4 SAUDI ARAMCO TUBE BUNDLE – 1 No. COMPLETED
JEDDAH REFINERY TUBE BUNDLE: J-C-E-226 SPLITTER NET OVERHEAD COOLER July-17
MATERIAL: 70/30 Cu Ni (UNS# C71500)
STATIONARY & FLOATING TUBE SHEET: SA516GR.70 + MONEL 400 WOL
TUBES – SB 111 UNS C 71500
BAFFLES & SUPPORT PLATE: 70/30 Cu Ni UNS# C71500
TIE ROD: SB 151 UNS# C 71500
SPACERS: UNS#71500
FLOATING HEAD COVER: 70/30 Cu Ni UNS# C71500
FLOATING HEAD FLANGE: 70/30 Cu Ni UNS# C71500
TUBE TO TUBE SHEET JOINT- EXPANSION JOINT
5 SATORP Re-tubing of Heat Exchanger 51-E-0026 – 1 No. TO BE COMPLETED
March-17
6 SAIPEM Scraper Traps – 7 Nos. TO BE COMPLETED
ARAMCO – Seven SSS Platform Decks, Pipelines and Cables Associated to Mrjn & Zulf Fields November-17
7 SAIPEM Scraper Traps – 1 No. TO BE COMPLETED
ARAMCO – SFNY 10 SLIPOVER JACKETS, 9 SLIPOVER DECKS, PIPELINES & CABLES ASSOCIATED T October-17
8 LUBEREF – E-1024B Tube Bundle – 1 No. TO BE COMPLETED
Saudi Aramco Base Oil Company September-17

EXPERIENCE LIST FOR MAJOR PROJECTS OF 2016 FOR PROCESS EQUIPMENT DIVISION

 

SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
1 SAUDI ARAMCO GAS MODULAR SKIDS – 33 Nos. TO BE COMPLETED
Various sites OIL MODULAR SKIDS – 40 Nos. March 2017
2 HANWHA SAUDI CONTRACTING CO. LTD OFFSHORE PILE WELDING WORK TO BE COMPLETED
JAZAN REFINERY & TERMINAL PROJECT (PKG-14) March 2017
3 SAIPEM – Chemical Dosing Packages – 13 Nos. TO BE COMPLETED
Snamprogetti Saudi Arabia Co. Ltd. June-17
SAUDI ARAMCO KHURAIS FAC. EXP. & SAT GOSP (SA)
4 SAIPEM – Chemical Dosing Packages – 4 Nos. TO BE COMPLETED
Snamprogetti Saudi Arabia Co. Ltd. July-17
SAUDI ARAMCO – Phosphate Injection Pkg – JIGCC Pkg 1
5 SAUDI ARAMCO VESSEL; PRESSURE TYPE (DESANDER) – 2 Nos. TO BE COMPLETED
Z009-C531 SHEDGUM LOCATION Shell OD 914 mm X Length 13,440 mm X 35 mm Thk. July-17
Shell MOC: SA 516 GR. 70N +HIC; ASME U2 Stamped
6 SAUDI ARAMCO Corrosion Inhibitor Injection Skids – 80 Nos. COMPLETED
November 2016
7 SAUDI ARAMCO METHANOL INJECTION SKIDs – 5 Nos. TO BE COMPLETED
Z011-C532 – UTHMANIYAH STORES March 2017
8 SAUDI ARAMCO SCRAPER TRAP : LAUNCHER (H92-D-0209) & TO BE COMPLETED
HRML -A Remote Header RECEIVER (H92-D-0210) – 10 Nos. October-17
9 SAUDI ARAMCO In-Situ Re-tubing and Repair Services – 1 No. TO BE COMPLETED
Ras Tanura Refinery November-19
10 Abener Abeinsa for Construction, HTF Tanks – 3 Nos. TO BE COMPLETED
Water and Power Co. Ltd. Max. Shell ID 3,7 m X Max. Lgth 25,350 mm X Max.28 mm Th August 2017
SEC – Waad Al-Shamal ISCCPP Project Shell MOC: SA 516 GR. 70
11 SAUDI ARAMCO CORROSION INHIBITOR INJECTION SKIDS – 5 Nos. TO BE COMPLETED
JUAYMAH CHEMICAL INJECTION SKIDS – 4 Nos. May 2017
12 CAT International Pressure Vessels – U Stamp – 2 Nos. TO BE COMPLETED
Shaybah Abqaiq Pipeline Capacity Shell ID 2,500 mm X T/T Length 9,570 mm X 16 mm Thk. May 2017
Saudi Aramco SA 516 GR. 70 + HIC
13 SAIPEM SpA Shell & Tube Heat Exchangers – 60 Nos. TO BE COMPLETED
Saudi Aramco – Jazan Integrated August 2017
Gasification Combned Cycle Project
14 TECNICAS REUNIDAS SHELL & TUBE HEAT EXCHANGERS – 6 Nos. – U stampe TO BE COMPLETED
ARAMCO – 10040 – September-17
FADHILI GAS PROGRAM PROJECT
15 TECNICAS REUNIDAS SHELL & TUBE HEAT EXCHANGERS – 10 Nos. – U stampe TO BE COMPLETED
ARAMCO – 10040 – February-17
FADHILI GAS PROGRAM PROJECT
16 SAUDI ARAMCO Upgrading Crude Royalty Metering System COMPLETED
RAS TANURA October-16
17 SAUDI ARAMCO Corrosion Inhibitor (CI) Package (Skid & Tank) – 1 No. TO BE COMPLETED
Safaniyah 24″ HDPE new water Oxygen Scavenger (OS) Package (Skid & Tank) – 1 No. March-17
disposal header line project
18 DENYS ARABIA COMPANY LTD. CLADDED PRESSURE VESSELS – 6 Nos. – U Stamped TO BE COMPLETED
ARAMCO – KHURSANIYAH Material: CS + INCOLOY 825 CLAD August-17
UPSTREAM GAS PIPELINES Flare Gas KO Drum – ID 3.4 m x TL to TL 7.3 m – 2 Nos.
Scraper Launcher Drain Vessel – ID 1.4 m x TL to TL 4 m – 2 Nos.
Pilot Gas KO Drum – ID 0.8 m x TL to TL 2 m – 2 Nos.
19 TARGET Construction Saudi Arabia VESSELS – 7 Nos. TO BE COMPLETED
CLOSED DRAIN SYSTEM AT ABQAIQ Max ID 3,962 mm x Max. Length 19,860 x Max. Thk 15 May-17
SAUDI ARAMCO Shell MOC: SA 516 GR 70N (HIC) – U Stamped
20 H.K. AL SADIQ SONS KNOCK OUT DRUM – 1 No. TO BE COMPLETED
Construction of PK TAIL GAS Project ID 1.6 m x TL to FF 2.7 m LG x 10 mm Thk March-17
Ar Razi, SABIC Shell MOC: SA 516 GR 70 – U Stamped
21 Sandvik Process Systems Skid Assembly – 4 Nos. – U stamped TO BE COMPLETED
ARAMCO – Jazan Refinery Terminal Project April-17
22 SAUDI ARAMCO SHELL REFINERY CO Heat Exchanger Bundles (E5301) and Mixer COMPLETED
(SASREF) Reaction Chamber (M5301) – 1 No. December-16
Page 3 of 28
23 SAUDI ARAMCO SHELL REFINERY CO Heat Exchanger Bundles/Accessories – 3 Nos. COMPLETED
(SASREF) Tube Bundle for Heat Exchanger E-7501A December-16
Tube Bundle for Heat Exchanger E-1404
New Channel Cover for Heat Exchanger E-7307
24 Al Robaya Holding Co. Scraper Traps (Launcher & Receiver) and TO BE COMPLETED
ARAMCO – Bahrain Pipeline Project – Jib Crane – 2 Nos. March-17
Onshore Contract
25 SAUDI ARAMCO Tube Bundle – 1 No. – U stamp COMPLETED
Riyadh Refinery R701-E-10 BENFIELD SOLUTION REBOILER December-16
Tube Sheet: SA 182 F304; Tubes: SA 213 TP 304;
Baffles & Support Plate: SA 516 Gr 60. ;
Tie Rod: SA 479 – SS 304; Tube to tube sheet joint: Expansion Joint.
26 TECNICAS REUNIDAS SHELL & TUBE HEAT EXCHANGERS – 4 Nos. – U stampe TO BE COMPLETED
ARAMCO – JIGCC – Utilities & Shell ID 2.25 M X 1.4 M (Kettle Type) x Tube length 6.1 M = 2 Nos. March-17
Common Area – Package 5 Shell ID 0.76 M x Tube length 4.4 M = 2 Nos.
Shell MOC: SA 516 GR 70N + HIC + NACE
Channels: SA 516 GR 70 N
Tubes: SA 334 GR 6;
27 HUSSAIN SALEH AL-MAHRI GEN. CON GASOLINE & DIESEL TANKS (UL 142) – 2 Nos. COMPLETED
ARAMCO – GAS STATION AT SHAYBA Shell MOC: SA 516 GR 70 February-17
Dia 2,408 mm x 8,992 mm LG x 8 mm Thk = 1 No.
Dia 1,707 mm x 5,181 mm LG x 8 mm Thk = 1 No.
28 SAUDI ARAMCO BLOW DOWN DRUM – 1 No. COMPLETED
Gas Treating Plant at Ras Tanura Dia 2,591 mm x 3,048 mm LG x 16 mm Thk December 2016
Shell MOC: SA 516 GR 70 + HIC – U Stamp
29 M.R. AlKhathlan Co. Deaerator Package – 1 No. TO BE COMPLETED
ARAMCO – Upgrade Sulfur Handling June-17
and Export Facilities at Berri Gas Plant
in Jubail Industrial Port [KFIP]
30 M.R. AlKhathlan Co. CONDENSATE SKID DRUM COMPLETED
Saudi Aramco – Shell MOC: SA 516 GR 70 N – ASME U stamped December-16
Upgrade Closed Drain and Dewatering Shell ID 1,600.2 mm X T/T Length 2,499.36 mm X 8 mm Thk.
System at Riyadh Refinery Shell MOC: SA 516 GR 70 N
31 M.R. AlKhathlan Co. AIR RECEIVER Vessel – 1 No. TO BE COMPLETED
ARAMCO – Upgrade Sulfur Handling Shell MOC: SA 516 GR 70 – ASME U stamped March-17
and Export Facilities at Berri Gas Plant Shell ID 1,219.2 mm X T/T Length 3,657.6 mm X 8 mm Thk.
in Jubail Industrial Port [KFIP]
32 SAUDI ARAMCO OVERHAUL & REPAIR OF VESSEL – 1 No. COMPLETED
MSSD Shop November-16
33 SAUDI ARAMCO Tube Bundle – 1 No. – U stamp COMPLETED
RAS TANURA PLANT J72 SULFUR J78-E-101 LEAN / RICH AMINE EXCHANGER November-16
Tube Sheet: SA 182 F304L; Tubes: SA 213 TP 304; Floating Head Dish/Flange:
SA 240 – 304L / SA182 F304L; Tie Rod: SA 479 – SS 304
34 SABIC Tank (TK-610) Bottom Plate Replacement – 1 No. TO BE COMPLETED
Ar-RAZI 31-Mar-17

EXPERIENCE LIST FOR MAJOR PROJECTS OF 2015 FOR PROCESS EQUIPMENT DIVISION

SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
1 SAUDI ARAMCO GAS MODULAR SKIDS – 10 Nos. COMPLETED
UTHMANIYAH STORES for OIL MODULAR SKIDS – 35 Nos. December 2016
KHUFF-Gas
2 SAUDI ARAMCO 027-D-301 CATALYST ADDITION POT – 1 No. COMPLETED
C001-E08 – RAS TANURA RED/ Dia 762 mm x 1,219.2 mm LG x 12 mm Thk November 2016
PU YARD Shell MOC: SA 516 GR 70 + HIC – U Stamp
3 SAUDI ARAMCO Tube Bundle – 1 No. – U stamp COMPLETED
C002-780/WH – JEDDAH REFINERY Tube Sheet: SA 516GR 70+MONEL 400 WOL November 2016
MAINT. B. WAREHOUSE Tubes: SB 111 C71500 (70/30 Cu/Ni); Baffles: SA 516 GR.70; Floating Head Dish /
Flange: SA 516 Gr.70 + Monel 400 WOL / SA 516 Gr.70 + Monel 400 WOL
4 SAUDI ARAMCO J80 SKID, METHANOL INJECTION SYSTEM – 1 No. TO BE COMPLETED
C0001-E08 – Ras Tanura RED/PU Yard 23-Apr-17
5 HQC (China Huanqiu Contr. & Eng. Co CS Spools (Galvanized Pipes and Fittings) COMPLETED
Proj. 51393 – UMM Wu’al Phosphate 29-Mar-16
Project, Beneficiation Plant, Crusher & Overland Conveyor – MA’ADEN
6 SAUDI ARAMCO JR LUBREF & SEC METERING SYSTEM UPGRADE & COMPLETED
JEDDAH REFINERY INSTALLATION – 1 No. March-16
7 SAUDI ARAMCO System: Metering; Liquid Custody Transfer Type COMPLETED
RAS TANURA RED/PU YARD – 1 No. July-16
8 TECNICAS REUNIDAS SHELL & TUBE HEAT EXCHANGERS – 22 Nos. – U stampe TO BE COMPLETED
ARAMCO – JIGCC – Utilities & Max. Shell ID 2,500 mm X Max. Length 7,000 mm March-17
Common Area – Package 5 Shell MOC: SA 516 GR 70; SA 106 GR B;
Tubes: SA 213 TP 304L; SA 334 GR 6; SA 179;
Tube Sheets: SA 266 GR 4 + SS 304L (CLADD); SA 266 GR 4 +
SS 304 L (CLADD); SA 350 LF2; SA 266 GR 2
Flanges: SA 105; SA 266 GR 2; SA 350 LF 2
9 HQC (China Huanqiu Contr. & Eng.  PRESSURE VESSELS – 12 Nos. – U stamped TO BE COMPLETED
Proj. 51393 – UMM Wu’al Phosphate Proj Max. Shell ID 3,200 mm X Max. Length 13,650 mm March-17
Beneficiation Plant, Crusher & Shell MOC: SA 516 GR 70
Overland Conveyor – MA’ADEN
10 M.R. AlKhathlan Co. SHELL & TUBE HEAT EXCHANGER (SWS-3 REBOILER) – COMPLETED
Saudi Aramco – (Z96-E-0206) – 1 No. – ASME U stamped November-16
Upgrade Closed Drain and Dewatering Shell ID 737 mm X Tube Length 4,87mm
System at Riyadh Refinery Shell MOC: SA 516 GR 70; Channel SA 516 GR 70 N + HIC + NACE; Tube Sheet:
SA 350 GR LF2; Tubes: SA 179; Flanges Tube/Shell side: SA 350 GR LF2 / SA 105
11 M.R. AlKhathlan Co. SW-3 Stripper Column (Tag# Z96-C-0202) – 1 No. – TO BE COMPLETED
Saudi Aramco – ASME U stamped March-17
Upgrade Closed Drain and Dewatering Shell ID 1,450 mm X T/T Length 27,800 mm X 10 & 12 mm Thk and 3.2mm Clad
System at Riyadh Refinery Shell MOC: SA 516 GR 70 N (HIC) + SS304 Clad
12 M.R. AlKhathlan Co. PRESSURE VESSELS – 6 Nos. – ASME U stamped COMPLETED
Saudi Aramco – with Process Guarantee for Multiphase Separator January-17
Upgrade Closed Drain and Dewatering Max. Shell ID 3,000 mm X Max. T/T Length 7,010 mm
System at Riyadh Refinery Shell MOC: SA 516 GR 70 N (HIC)
13 SAUDI ARAMCO SCRAPER – LAUNCHER & RECEIVER – 4 Nos. COMPLETED
Oil Wells # Shyb Increment – October-16
Delivery to SHEDGUM STORES
14 RESEARCH-COTTRELL DRY COOLI PIPING SPOOLS FABRICATION – (CS & SS) COMPLETED
SEC – 2×2 Air Cooled Codensers for 31,648 DIA INCH September-16
Power Plants, Riyadh, PP13 & PP14
15 SAUDI ELECTRICITY COMPANY SCRAPER TRAP / HANDLING FAC/JIB CRANE – 2 Nos. TO BE COMPLETED
FUEL GAS PIPELINES AT PP13 COMBINED CYCLE POWER PLANTS March-17
16 SAUDI ARAMCO SCRAPER – LAUNCHER & RECEIVER – 2 Nos. COMPLETED
UTHMANIYAH STORES December-16
17 SAUDI ARAMCO SCRAPER TRAPS, HANDLING FACILITY, JIB CRANE & TO BE COMPLETED
PIPELINE NORTHERN AREA PASSAGE INDICATORS – 2 Nos. February-17
(SBCL-2 PIPELINE)
SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
18 LARSEN TOUBRO ARABIA L.L.C. PIPE SPOOL FABRICATION (CS) – 33,701 Dia Inch COMPLETED
ARAMCO – MIDYAN GAS PROCESSING FACILITIES (MGPF), March-16
MIDYAN, TABUK PROVINCE , KSA.
19 SAUDI ARAMCO SCRAPER – LAUNCHER & RECEIVER – 2 Nos. COMPLETED
ABQAIQ STORES August-16
20 SAUDI ARAMCO Upgrade Tube Bundle 101-E26 A/B – 2 Nos. COMPLETED
RIYADH PROJECTS Shell ID x Tube L: 950mm x 6,100mm; Tubes: SA 268 TP 410; March 2016
Stationary & Floating Tube Sheets: SA 182 F 6 a; Baffles: SA 240 TP 410S; Tie Rod: SS 410
21 SAUDI ARAMCO Tube Bundles – 813-E1A/B – 2 Nos. – U stamped COMPLETED
RIYADH T&I Tube sheets: A 182 F304 May 2016
Tube Material: ASTM A213 TP321 SS
Baffles ASTM A283-C; Tie rods ASTM A675
22 SAUDI ARAMCO U Tube Bundle – 1 No. – U stamp COMPLETED
UTHMANIYAH REFINERY Tube Sheet: SA 105+SS316L CLAD May-16
Tubes: SA 249 TP 316L; Baffles: SA 240 GR.316L
23 SEPCO Electric Power Construction C Condensate / Feedwater Heat Exchangers – 10 Nos. COMPLETED
Jazan IGCC Power Block Project Shell & Dish End: SA 516 GR 70; Channel: SA 182 F 316L; November-16
(Pkg. 4) Tube Sheet: SA 266 GR 2 + SS 316 L (WOL).; Tubes: SA 213 TP 316L;
Nozle Flange (Shell Side – SA105) (Channel Side – SA 182 F 316L)
Baffles: SA 516 GR 70; Tie Rods SS316; Spacer SS 316 – ASME U2 Stmp
24 HANWHA SAUDI CONTRACTING CO. L Field Auto Welding, fit-up including grinding for TO BE COMPLETED
ARAMCO – Jazan Reifinery and 18″ over pipe line and support in the jobsite. August-17
Terminal Project, Pkg#14
25 SEPCO ELECTRIC POWER PRESSURE VESSELS – 9 Nos. COMPLETED
SHAYBAH COMBINED CYCLE Max. Dia 1,520 mm X Max. 7,100 mm Height X Max. Thk.16mm November-16
POWER GENERATION PROJECT SA 516 Gr.70 – ASME U Stmp
26 SAUDI ARAMCO HEAT EXCHANGER – TUBE BUNDLE – 1 No. COMPLETED
RAS TANURA REFINERY TUBE SHEET SA350 LF2 + INCONEL 625 OVERLAY; October-15
TUBES: SA 213-UNS-S31254 – ASME “U” Stamp
SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
27 SIPCHEM FURNACE HEATERS – 3 Nos. – (380 Tons each) COMPLETED
Material SS & P11 October-15
ASME U Stmp
28 SAUDI ARAMCO SCRAPER – LAUNCHER & RECEIVER – 2 Nos. COMPLETED
UTHMANIYAH STORES December-16
29 PETRO RABIGH Tube Bundle for H.EX. 5300-E23 – 1 No. COMPLETED
Rabigh Refining and Petrochemical Co. Tube Sheet – SA 105 & Tubes SA 179 December-15

EXPERIENCE LIST FOR MAJOR PROJECTS OF 2013-2014 FOR PROCESS EQUIPMENT DIVISION

 

SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
1 SAUDI ARAMCO Corrosion Inhibitor Injection Skid – 70 Nos. COMPLETED
UTHMANIYAH STORES June-15
2 JGC Gulf Engineering Co. Ltd. CUSTODY METERING SKIDS – 3 Nos. & COMPLETED
REHABILITATION OF AMT PROJECT – PROVER 1 No. July-16
AL MUAJJIZ TERMAINAL YANBU – ARAMCO
3 SAUDI ARAMCO HEAT EXCHANGER – CHANNEL HEAD & FLOATING HEAD COMPLETED
4 Nos. ASME “U” Stamp December-15
MOC: SA 516 GR 70 + MONEL OVERLAY
4 SK Engineering & Construction TRANSFER LINES (CLAD SPOOL 70″ & 145″) COMPLETED
ARAMCO – JRTP Pkg #9 October-16
5 CAT SURGE RELIEF SKIDS – 6 Nos. COMPLETED
ARAMCO – INCREASE RIYADH – August-15
QASSIM (RQ1) PRODUCT PIPE LINE
6 SABIC (Saudi Basic Industries Corpor DRIP VESSELS – 5 Nos. COMPLETED
SHARQ SHELL ID 2,000 mm x Length 2,500 mm x Thk 6mm March-15
MOC: SA 516 Gr. 70 & SA 240 TP 304
7 SABIC TUBE BUNDLES – 2 Nos. COMPLETED
Ethylene Plant SADAF (Saudi Petrochem Tubes: Welded Titanium Tubes B 338 Gr 2 (Fin Tubes); Tube Sheet: SA 266 CL4 + Claded w May-15
Floatng Head Dish: SA 516 Gr.70 with Monel 4400 (Weld Over Lay; Baffles: SA 516 Gr.70
8 PETROFAC SAUDI ARABIA CO. LTD. TRUCK LOADING SYSTEM – 7 Nos. TO BE COMPLETED
JAZAN REFINERY & TERMINAL PROJE March-17
(North Tank Farm & Loading Facilities) ARAMCO
9 SAUDI ARAMCO SCRAPER TRAP: LAUNCHER AND RECEIVER – COMPLETED
TANAJIB (MRJN GOSP-1, ZULUF TP-3, 3 Nos. June-15
ZULF GOSP-2, SFNY 369 (Onshore)
SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
10 VEOLIA WATER PIPE SPOOL FABRICATION – 12,900 Dia Inch COMPLETED
LUBEREF YANBU REFINERY SS304L PIPE SPOOLS/SS316 PIPE SPOOLS/ June-15
EXPANSION AIR PIPE SPOOLS
11 DRAGADOS GULF CONSTRUCTION DIESEL LOADING SKIDS – 2 Nos. COMPLETED
LOADING RACK FACILITY PROJECT @ July-15
RAS TANURA – SAUDI ARAMCO
12 SAUDI ARAMCO CHEMICAL INJECTION PUMP SKID UNIT – 1 No. COMPLETED
TANAJIB STORES August-15
13 SAUDI ARAMCO CORROSION INJECTION SYSTEMS – 2 Nos. COMPLETED
UTHMANIYAH STORES December-14
14 SAUDI ARAMCO CHANNEL BOX (COVER) – 4 Nos. COMPLETED
YANBU REFINERY Shell ID 1,350mm x Length 1,109mm December-15
SHELL: SA516 GR.70 CLADDED WITH SB 127 UNS NO 4400
FLANGES: SA 350LF2CL1 UNS NO 4400 OVERLAY
15 SABIC RIK 4 BUNDLE TUBES FOR 2 HEAT EXCHANGERS COMPLETED
SADAF PROJECT SITE (LSTK Project) REPLACE TUBES FOR 4 BUNDLES – “U” & “R” STAMP December-14
16 SNAMPROGETTI, SAUDI ARABIA SLOP TANKS – 3 Nos. & Neutralization Tank – 1 No. COMPLETED
MARJAN ZULF PROJECT SA 516Gr.60+HIC / SA 36 / SS316L – UL-142 February 2015
SAUDI ARAMCO
17 SNAMPROGETTI, SAUDI ARABIA SLOP TANKS – 3 Nos. COMPLETED
DECKS, PIPELINES & CABLES Dia 1,656 mm x 5,500 mm LG x 10 mm Thk August-14
AT ABU SAFAH – ARAMCO SA 36 – UL-142
18 SAUDI ARAMCO FUEL OIL METERING SKID, METER PROVER SKID, COMPLETED
YANBU REFINERY DENSITY MEASUREMENT SKID AND AUTO SAMPLER – November-16
Total 4 Nos.
SL NO. CLIENT DESCRIPTION OF WORK COMPLETION
19 SAUDI ARAMCO DYE INJECTION SKID with Installation ( Civil, COMPLETED
RABIGH REFINERY Electrical, Mecanical & Instrumentation) – LSTK Contract June-15
(Inst. New Color Injection Skid, Rabigh) – 1 No.
20 SAUDI ARAMCO VERTICAL AIR RECEIVER – 1 No. COMPLETED
SAFANIYAH OFFSHORE Dia 355 mm x 1,800 mm LG x 8 mm Thk February-14
ASME “U” Stamp, SA 106 GR.B
21 SABIC Replacement of Bottom Plate & COMPLETED
IBN AL-BAYTAR Annular Plate on U-301F & U-401F Tanks – 2 Nos. March-14
22 SAUDI ARAMCO CORROSION INHIBITOR INJECTION UNIT – 3 Nos. COMPLETED
TANAJIB March-15
23 RESEARCH-COTTRELL DRY COOLI PIPING SPOOLS FABRICATION COMPLETED
PP10 PROJECT 43,000 Dia Inch May-14
24 ALSTOM POWER SYSTEM STACKS – 6 Nos. COMPLETED
SADARA PROJECT Dia 3,429 mm x 76,200 mm LG February-14
SA 36
25 FLUOR ARABIA LIME AND BYPRODUCT SILOS – 12 Nos. COMPLETED
SADARA PROJECT STEAM GENERATI Dia 8,000 mm x 35,135 mm LG May-14
SA 36
26 UHDE ARABIA LTD. THF PSV Discharge Condenser (21-E-6009) – 1 No. COMPLETED
SIPCHEM PBT PROJECT Shell ID 0.83 Mtr. x 6,400 mm LG February-14
ASME “U” Stamp, SA 516 GR.60N, Tubes – SA179
27 UHDE ARABIA LTD. THF PRODUCT STORAGE CS VESSEL (IDC) – 1 No. COMPLETED
SIPCHEM PBT PROJECT Dia 5,400 mm x 16,200 mm LG x 20 mm Thk April-14
ASME “U” Stamp, SA 516 GR.60N
28 UHDE ARABIA LTD. THF PRODUCT STORAGE SS VESSEL – 1 No. COMPLETED
SIPCHEM PBT PROJECT Dia 4,100 mm x 12,300 mm LG x 12 mm Thk April-14
ASME “U” Stamp, SS 304L
29 SAUDI ARAMCO TUBE BUNDLE – 1 No. COMPLETED
RIYADH T&I UNIT TUBE SHEET SA 182F11+SA266 Gr.2, August-16
TUBE: SA199 T 11,
30 ARASCO SILOS – 163 Nos. COMPLETED
DAMMAM & ALKHARJ FEED MILLSMax. Dia 3,500 mm x Max. Height 21,000 mm x Max. 6 mm Thk December-13
Material: SA 36
31 SAUDI ARAMCO CHANNEL BOX – 3 Nos. COMPLETED
YANBU REFINERY Channel Shell: SA 516 Gr.60 cladding of SB171-C71500; April-15
Partition Plate: SB171-C71500;
32 SAUDI ARAMCO TUBE BUNDLE – 1 No. COMPLETED
M002-108 – DHAHRAN DH RECEIVING TUBE SHEET SA 182F11+SA240 TP SS410 CLAD, April-14
TUBES: SA268 TP 410
33 SAUDI ARAMCO TEG RE-BOILER F-161/261 – 2 Nos. COMPLETED
MARJAN OFFSHORE ENGINEERING U ASME “U” Stamp July-14
SA 516 Gr.70 HIC
35 SAMSUNG ENGINEERING Repair of damaged Air Dryer Package for NGL
Shaybah Package #2 NGL Recovery and Recovery and Utilities Project – 1 Unit
Utilities Project, Saudi Aramco